Bernalillo County Commercial Building & Structural Permit Calculator
Official fee schedule logic based on Albuquerque City Code Chapter 14. Includes plan review fees, technology surcharges, and prerequisite contractor bond rules.
- AHJ Authority
- City of Albuquerque Planning Dept Building Safety
- Enforced Ordinance
- Albuquerque City Code Chapter 14
- Plan Check SLA
- 10 - 15 Business Days
- Surety Bond Required
- $10,000
Bernalillo County Commercial Permit Fee Estimator
Tier Valuation Formula: $1,665 base fee + $3.80 per $1,000 above $250,000 valuation.
Mandatory Contractor Prerequisites & Submittal Checklist
Bernalillo County AHJ RequirementsContractor Surety License Bond
Bernalillo County requires an active $10,000 New Mexico CID Contractor License Bond on file prior to plan submittal.
Commercial COI Liability ($1M+)
Minimum $1.0M General Liability COI naming Bernalillo County Building Dept as Certificate Holder.
Commercial Building & Structural Submittal Rules in Bernalillo County
Specialized trade submittals for Commercial Building & Structural in Bernalillo County, New Mexico are administered by City of Albuquerque Planning Dept Building Safety. Permits are required prior to installing, extending, replacing, or altering any mechanical, electrical, plumbing, structural, or life-safety infrastructure under Albuquerque City Code Chapter 14.
Intake review for Commercial Building & Structural requires verified trade licensing, minimum contractor general liability COI filings ($1,000,000+), and compliance with enforced regional code editions (2021 New Mexico Commercial Building Code.).
Mandatory Submittal Plan Documents & PE Engineering Stamps
Plans submitted to City of Albuquerque Planning Dept Building Safety for Commercial Building & Structural must include scaled engineering drawings and specifications:
- NM Licensed Architect Stamp
Inspection Sequence for Commercial Building & Structural
Work performed under a Commercial Building & Structural permit in Bernalillo County requires mandatory rough-in and final field inspections. Rough-in inspections must be conducted and signed off by the municipal inspector prior to covering or concealing any piping, ductwork, structural framing, or electrical conductors. Final inspection and system testing are required for building certificate of completion issuance.
City of Albuquerque Planning Dept Building Safety Official Building Department
600 2nd St NW, Albuquerque, NM 87102 | Phone: (505) 924-3650